Public meeting — April 15, 2026

Cemetery Street Traffic Decision · 6:30 PM · Upper Town Hall

On April 15, the Select Board will hear from the Town's experts (Highway, Police, Fire, and Tighe & Bond), weigh options for Cemetery Street traffic, and discuss next steps. The Board may outline future options for detours and traffic management as more information becomes available.

The Board reserves the right to adjust plans based on new information, field conditions, or safety needs — up until active construction begins. What is decided on April 15 is not necessarily frozen for the entire project if circumstances change.

Submit questions in advance by emailing bosadmin@mendonma.gov by end of day Thursday, April 9th. Agenda posted at the Agenda Center 48 hours before the meeting.

Mendon, Massachusetts

Providence Street Culvert Replacement

Clear information for Mendon residents about the culvert project, detours, timeline, and how decisions are made.

$2.1M

Project investment

19 ft

New culvert span

75+ yrs

Design lifespan

2026

Completion target

Last updated:

Quick briefing

What residents need first

The Town is replacing the Providence Street culvert — the aging drainage structure beneath Providence Street that carries Spring Brook under the road. Spring Brook overtopped its banks during high-intensity storms in late 2023 and again in spring 2024, flooding the road and making clear that the existing corrugated metal pipes can no longer handle current storm flows safely. Work of this kind is disruptive by nature.

This page explains why the replacement is necessary, how traffic will be managed during construction, what to expect over the project period, and how the Town reached its decisions — including the active question many neighbors have raised about Cemetery Street and whether it should carry one-way or two-way traffic as a detour.

The engineering firm is Tighe & Bond. Project completion is expected in 2026.

If anything here conflicts with a posted order, police detail, or signed document from the Town, follow the official posting and contact the Highway Department or Town Hall.

Current phase

Permitting and procurement

Winter 2026 through summer 2026

At a glance

Project summary

One-page overview of scope, safety rationale, and mitigation — complements the written sections below.

Providence Street Culvert Project: Prioritizing Community Safety — overview of road closure, legal context, funding, map of the closure area, mitigation costs and measures, and safety-first rationale including emergency response.
Download full infographic (PNG)

If dates or figures on the graphic differ from this site, treat the Timeline and FAQ as current.

Detour and traffic

Current route, one-way/two-way context, and map references.

Timeline and phases

Where the project stands today and what comes next.

Open questions

What is resolved versus still pending Board action.

Frequently asked questions

Direct answers to the most common resident concerns.

Decision process

How engineering, legal, and board decisions were made.

Project details

Old vs. new structure, funding, and engineering rationale.

Project area

Where it's happening

Providence Street at Spring Brook, Mendon, MA — satellite view. Full detour routes on the Detour page.

Providence Street project area — Mendon, MA (satellite view)

Bridge location: Providence St at Spring Brook crossingProposed detour: Cemetery St (one-way per engineering rec.)

Full diagram and routing on the Official documents page.

Open now

  • Cemetery Street traffic direction
  • Construction schedule
  • Signed detour routes and field signage
View all open items

Most searched questions

  • Why does Providence Street have to close completely?
  • What is the detour route?
  • Why one-way on Cemetery Street instead of two-way?
  • Is the one-way recommendation final? What about the two-way proposal?
Open full FAQ